61-2026-00000112
Reduce greenhouse gas emissions
Перевод на природный газ обжиговой печи ООО "Серебрянский цементный завод"

The number of carbon units released within the framework of the climate project

0
25.04.2023beginning of the offset period
24.04.2033end of the offset period
1 822 685
Planned
amount of reduction
1 822 685
CU planned for release
0
CU in circulation within the CP
0
CU offsetted

General information

Executor
ООО "СЕРЕБРЯНСКИЙ ЦЕМЕНТНЫЙ ЗАВОД", OGRN 1036224001087 dated 31.07.2003
State
Active
Executor location address
391720, Рязанская обл, Михайловский р-н, рп Октябрьский, ул Кооперативная, 1
Industry affiliation of the climate project (in accordance with OKVED)
23.51
Current status of the climate project (information on the climate project implementation)
-

Climate project deadlines

Climate project implementation period
25.04.2023-28.02.2043
Actual climate project start date
25.04.2023
Scoring period
25.04.2023 - 24.04.2033

Validation information

Report on the compliance of the project with the criteria for project classification
Общество с ограниченной ответственностью Малое инновационное предприятие «Национальный центр валидации и верификации экологической информации Института глобального климата и экологии», OGRN 1237700314334, unique accreditation record number in the register of accredited persons RA.RU.150044 dated 2026-02-27
Number and date of report
ВА-ПГ-01 dated 2026-02-27
Number and date of the validation report
ВА-ПГ-01 dated 2026-02-27

Location addresses

Labels

No labels

Roadmap

project icon

Completion of the climate project

28.02.2043