36-2025-00000050
Reduce greenhouse gas emissions
Technical re-equipment of the IP-3 unit. Transfer of the MTBE-1 unit blowdown to the suction of the TK-403 "Viola" turbocharger of the BK-3 unit to reduce hydrocarbon feedstock losses.

The number of carbon units released within the framework of the climate project

0
20.05.2022beginning of the offset period
19.05.2027end of the offset period
13 623
Planned
amount of reduction
13 623
CU planned for release
0
CU in circulation within the CP
0
CU offsetted

General information

Executor
LLC Tolyattikauchuk, OGRN 1026301984862 dated 07.10.2002
State
Active
Executor location address
445007, Samara Region, Tolyatti, Novozavodskaya Street, 8
Industry affiliation of the climate project (in accordance with OKVED)
20.14.1
Current status of the climate project (information on the climate project implementation)
A positive conclusion on the project's compliance with the criteria for climate projects has been received from greenhouse gas validation and verification authority ANO VPO 'University Innopolis' . The implementation of the project is in progress.

Climate project deadlines

Climate project implementation period
25.02.2022-19.05.2037
Actual climate project start date
-
Scoring period
20.05.2022 - 19.05.2027

Validation information

Report on the compliance of the project with the criteria for project classification
Authority for validation and verification of greenhouse gas ANO VPO "University Innopolis", OGRN 1121600006142, unique accreditation record number in the register of accredited persons RA.RU.150004 dated 2025-02-14
Number and date of report
RU V-RU.150004.0.00012/25 dated 2025-02-14
Number and date of the validation report
RU V-RU.150004.0.00012/25 dated 2025-02-14

Location addresses

Labels