47-2025-00000083
Reduce greenhouse gas emissions
Reduction of greenhouse gas emissions due to the modernization of the Verkhne-Tulomskaya Hydroelectric Power Plant (HPP-12) of PJSC TGK-1 with an increase in installed capacity

The number of carbon units released within the framework of the climate project

8 353
01.01.2022beginning of the offset period
31.12.2031end of the offset period
48 468
Planned
amount of reduction
48 468
CU planned for release
8 353
CU in circulation within the CP
0
CU offsetted

General information

Executor
PJSC "TGK-1", OGRN 1057810153400 dated 25.03.2005
State
Active
Executor location address
197198, St. Petersburg, Dobrolyubova Avenue, Building 16, Office 2A, Room 54N
Industry affiliation of the climate project (in accordance with OKVED)
35.11
Current status of the climate project (information on the climate project implementation)
The first reporting period for the climate project (January 1, 2022 - December 31, 2024) has now been completed, the results of which are reflected in the Climate Project Implementation Report. The report received an unconditional (positive) conclusion from the Validation and Verification Body. The climate project continues to be implemented in the second reporting period.

Climate project deadlines

Climate project implementation period
06.07.2021-31.12.2031
Actual climate project start date
06.07.2021
Scoring period
01.01.2022 - 31.12.2031

Validation information

Report on the compliance of the project with the criteria for project classification
Validation and verification body LLC "KEPT Verification", OGRN 1227700447186, unique accreditation entry number in the register of accredited persons, OGRN 1227700447186, unique accreditation record number in the register of accredited persons RA.RU 150049 dated 2025-10-23 dated 2025-10-23
Number and date of report
2025-0002-КВ dated 2025-10-23
Number and date of the validation report
2025-0002-КВ dated 2025-10-23

Location addresses