Construction of a gas pipeline from BPS-6s to the Devonian gas pipeline from BPS-6a NGDU "Elkhovneft"
Name of the legal entity/Last name, first name and patronymic (initials) of the individual, including an individual entrepreneur
PAO “TATNEFT” NAMED AFTER V.D. SHASHIN
Location address
Ulitsa Lenina, 75, Almetyevsk, Respublika Tatarstan, 423450
Form of incorporation (for legal entities)
Public joint stock companies
Principal State Registration Number and its registration date (if any) (for Russian legal entities)
1021601623702 19.07.2002
Unique climate project number
92-2024-00000015
Current status of the climate project (information on the climate project implementation)
An accredited person of OOO MIP NES Profexpert has issued a positive conclusion on the compliance of the project with the criteria for climate projects. The climate project is being implemented and monitored.
Total number of carbon units in circulation within the climate project
2170
Number of carbon units planned for release into circulation upon registration of the climate project
23750
Planned reduction in (or prevention of) greenhouse gas emissions and/or increase in greenhouse gas absorption as a result of the climate project implementation
23750
Climate project implementation period
01.09.2021-31.12.2031
Planned climate project start date
01.09.2021
Actual climate project start date
Planned climate project end date
31.12.2031
Information about the period, when reduction in (or prevention of) greenhouse gas emissions and/or increase in greenhouse gas absorption takes place as a result of the climate project implementation
01.01.2022 - 31.12.2031
Climate project implementation site (location of the land plot(s) where the climate project is implemented, including the address and/or geographical indication)
The project for the construction of a gas pipeline from BPS-6s to the Devonian gas pipeline from BPS-6a NGDU Elkhovneft is being implemented in the Zainsky district of the Republic of Tatarstan, 2.4 km northwest of the village Alexandrovskaya Sloboda.
16:19:170105:634

the code of the subject of the Russian Federation at the location of the climate project (OKATO): 92
Information on the favorable opinion on the compliance of the project with the classification criteria for climate projects, issued by an accredited organization (name and principal state registration number of the accredited organization, details of the favorable opinion (date and number), name and unique number of the record in the accredited organizations register)
OOO MIP NES Profexpert OGRN 1201600019048
Conclusion on validation from 30.01.2024
№4
Industry affiliation of the climate project (in accordance with OKVED)
06.10
Information on the accredited organization (name and unique number of the record in the accredited organizations registry)
RA.RU.150010
Information on verification of the results of climate project implementation (climate project implementation report date and details, verification statement date and the final opinion of the accredited organization)
Climate Project Implementation Report No. 9629-ish dated 28.05.2024, date of signing of the verification report 12.07.2024. Final conclusion of the Accredited Person: In accordance with the verification performed, the statement on the reduction of greenhouse gas emissions as a result of the implementation of the climate project is found to a reasonable degree of certainty: - is found to be credible and accurately reflects greenhouse gas data and information, - prepared in accordance with the requirements of relevant documents on quantification and monitoring of greenhouse gas emissions. The predicted (baseline) mass of GHG emissions for the reporting period that could have been generated without the implementation of the climate project was 2,174 tCO2-eq. The actual mass of greenhouse gas emissions was 4 tCO2-eq. The mass of greenhouse gas emission reductions was 2,170 tCO2-eq. Number of carbon units released: 2,170.
Public information