Construction of the 4 t/h liquefied carbon dioxide plant to reduce greenhouse gas emissions
Name of the legal entity/Last name, first name and patronymic (initials) of the individual, including an individual entrepreneur
AO "NAK "AZOT"
Location address
301651, Tula Region, Novomoskovsky district, Novomoskovsk, st. Svyazi, 10
Form of incorporation (for legal entities)
Non-public joint-stock companies
Principal State Registration Number and its registration date (if any) (for Russian legal entities)
1027100507378 29.10.2002
Unique climate project number
70-2023-00000005
Current status of the climate project (information on the climate project implementation)
At present, the first reporting period for the implementation of the climate project has been completed, the results of which are reflected in the verified Report on the implementation of the climate project "Construction of the 4 t/h liquefied carbon dioxide plant to reduce greenhouse gas emissions" for the first reporting period 09.2022 - 03.2023 in the form, approved by the order of the Ministry of Economic Development of Russia dated May 11, 2022 No. 248 and in accordance with the requirements of GOST R ISO 14064-2-2021. The implementation of the climate project continues.
Total number of carbon units in circulation within the climate project
12392
Number of carbon units planned for release into circulation upon registration of the climate project
583995
Planned reduction in (or prevention of) greenhouse gas emissions and/or increase in greenhouse gas absorption as a result of the climate project implementation
583995
Climate project implementation period
01.09.2022-31.08.2042
Planned climate project start date
01.09.2022
Actual climate project start date
Planned climate project end date
31.08.2042
Information about the period, when reduction in (or prevention of) greenhouse gas emissions and/or increase in greenhouse gas absorption takes place as a result of the climate project implementation
01.09.2022 - 31.08.2042
Climate project implementation site (location of the land plot(s) where the climate project is implemented, including the address and/or geographical indication)
The Tula Region, Novomoskovsky district, Novomoskovsk, st. Svyazi, 10, industrial site of JSC «NАК «АZOT»
71:29:020501:1577

the code of the subject of the Russian Federation at the location of the climate project (OKATO): 70
Information on the favorable opinion on the compliance of the project with the classification criteria for climate projects, issued by an accredited organization (name and principal state registration number of the accredited organization, details of the favorable opinion (date and number), name and unique number of the record in the accredited organizations register)
«PROMMASH TEST ECOLOGY» LLC OGRN 1137799011074
Conclusion on validation from 03.04.2023
б/н
Industry affiliation of the climate project (in accordance with OKVED)
20.15
Information on the accredited organization (name and unique number of the record in the accredited organizations registry)
Authority for validation and verification of greenhouse gas «PROMMASH TEST ECOLOGY» LLC RA.RU.150007
Information on verification of the results of climate project implementation (climate project implementation report date and details, verification statement date and the final opinion of the accredited organization)
Date of preparation of the report on the implementation of the climate project and its details "Report on the implementation of the climate project: "Construction of the 4 t/h liquefied carbon dioxide plant to reduce greenhouse gas emissions" for the period - September 2022 - March 2023 Version 2" dated 03.04.2023. Date of signing the conclusion on verification of 08.04.2023. Final conclusion of the accredited person as a result of initial and first periodic verification, based on the completed verification procedures, PROMMASH TEST ECOLOGY LLC confirms, that the quantitative assessment of greenhouse gas emissions reduction is carried out with satisfactory accuracy and does not contain significant errors and omissions. Our expert opinion concerns greenhouse gas emissions within the Project and their reduction in relation to the amount of emissions that would be most likely to occur in the absence of project activities (Baseline). Based on the completed verification procedures, we confirm that the quantitative assessment of greenhouse gas emissions reduction was carried out in accordance with the methodology for assessing greenhouse gas emissions reductions and the monitoring plan confirmed earlier during the validation of project activities. Based on the information that we received and evaluated, we confirm with a reasonable degree of assurance the following conclusion: The data of the climate project implementation report are reliable (positive conclusion).
Public information